[Detailed design for improvement of a sewer between 13 and 32 in Yeouido ]
07.05.02 ~ 07.07.16 / Yeongdungpo ward office
The purpose of this project is to secure a comfortable life for a residents of #13~23 region in Yeouido, as improving a decrepit and bad sewer, and relocating it to be overlapped with a existing utility tunnel between #13 and 23 in Yeouido-dong.
The total length of the sewer is 0.5km. Section of a lower part of a utility tunnel that is crossing with a existing pipe and a park that is difficult to construct has been planned a way of using a steel pipe. As one part of the project will be newly constructed for a exclusive pipe in order to avoid overlapping with a utility tunnel, the flow of sewage would be distributed from a existing sewer and it has been planned for the sewage water to flow smoothly.
|