Preliminary Environmental Investigation for Privately Funded 2nd Outer Ring Road (Icheon - Osan) Exp |
Preliminary Environmental Investigation for Privately Funded 2nd Outer Ring Road (Icheon - Osan) Expressway
Period : 2008.01 ~ 2013.12
Ordering Organization : Ministry of Land, Transportation and Maritime Affairs
- The project route was 29.7 km long, 4 lanes in both directions, regional highway National Road, connecting Gyeongbu Expressway in Hwaseong with Jungbu Expressway in Icheon. It will form a part of the 2nd Outer Ring Road for Seoul Metropolitan area, diverting traffic from the city, alleviating congestion, and connecting the south-north arterial road network (Gyeongbu, Jungbu and Jungbu Naeryuk Expressways) with the east-west arterial road network (Yeongdong, 2nd Gyeongin Expressways) and the 1st Outer Ring Road. It will divert freight transportation from the Gyeongbu and Yeongdong Expressways, and promoted balanced regional development. - In order to minimize the environmental impacts from the construction of the expressway, route was selected so that it would avoid damage to forests, and countermeasures against environmental impacts were established. |
|
|
|
|
Basic Design (Turnkey) for Tancheon Water Recycling Advanced Treatment Facilities |
Basic Design (Turnkey) for Tancheon Water Recycling Advanced Treatment Facilities
Period : 2008.08.08 ~ 2008.12.09
Ordering Organization : Daelim Industrial Co., Ltd.
- The Tancheon facility will have a capacity of 900,000 cubic meters per day, using MLE advanced treatment method and 3rd treatment facility to conform to the water quality standards for water discharge. - As part of the "Creative Ecological City" initiative of the Seoul Metropolitan Government, this project planned a complete water treatment facility for the water discharges. It will improve the water quality of Tancheon stream and Han River. The facilities provide highly efficient, low-cost treatment, improving the health of the residents, and includes environmental education center, green leisure areas, and an ecological conservation area. |
|
|
|
|
Basic Design for Privately Funded (BTO) Gimpo Sewage Facilities Project |
Basic Design for Privately Funded (BTO) Gimpo Sewage Facilities Project
Period : 2008.01 ~ 2008.02
Ordering Organization : Daelim Industrial Co., Ltd.
�� With the rapid growth of population in GImpo due to the development of residential zones and new towns, expansion of the sewage systems is necessary. This project was promoted as a privately funded project. �� With the improved treatment, pollution will be reduced, and water quality improved on the Han River system, which has been the receiving body of water for the human sewage discharges. �� Efficient maintenance system was established and stability ensured with an appropriate and well operated sewage treatment site construction. |
|
|
|
|
Basic Design for Privately Funded (BTO) Gimpo Sewage Facilities Project |
Basic Design for Privately Funded (BTO) Gimpo Sewage Facilities Project
Period : 2008.01 ~ 2008.02
Ordering Organization : Daelim Industrial Co., Ltd.
�� With the rapid growth of population in GImpo due to the development of residential zones and new towns, expansion of the sewage systems is necessary. This project was promoted as a privately funded project. �� With the improved treatment, pollution will be reduced, and water quality improved on the Han River system, which has been the receiving body of water for the human sewage discharges. �� Efficient maintenance system was established and stability ensured with an appropriate and well operated sewage treatment site construction. |
|
|
|
|
Basic Design for Lease-Type Privately Funded (BTL) Goesan County Sewage Maintenance |
Basic Design for Lease-Type Privately Funded (BTL) Goesan County Sewage Maintenance
Period : 2007.11.05 ~ 2008.02.04
Ordering Organization : Kyeryong Construction Industrial Co., Ltd.
- The project comprises a total area of 191.27 ha, with a total length of 49,149 m of sewage pipes, and 3,630 drainage facilities. Works included the complete rehabilitation of the sewage pipes, and will result in the improvement of the operating efficiency of Goesan and Cheongcheon sewage treatment facilities, reduction of infiltration/inflow (I/I), improvement of ground water quality, vitalization of the regional economy in Goesan County, and efficient maintenance by using a comprehensive monitoring system. - Using private financing for the project will allow Goesan County to improve its environment, while maximizing the benefits, and reducing stress on the public budget. |
|
|
|
|
Water Supply and Sewage Turnkey Works for Gwangyang Port Western Site (Lot 1) Development |
Water Supply and Sewage Turnkey Works for Gwangyang Port Western Site (Lot 1) Development
Period : 2007.05.10 ~ 2007.06.23
Ordering Organization : Posco Construction
�� Location: Wester Site for Gwangyang Port Container Wharf in Jeollanam Province �� Scope: 1,078,833 square meters �� Works: Water supply L=8,262 m, sewage L=12,972 m �� Project goals: - The project is based on the strategy of strengthening national economy by port industries and plan for construction of the port to become a central business hub of Northeast Asia. The development of a international multi-modal logistics park to connect with the container port was promoted. - Rainwater treatment equipment was planned, due to the increase of outflow and pollution from the site development. Water quality should be improved in the receiving area of the effluent (streams and lakes). Vacuum sewage system was installed to prevent sewage seepage and minimize excavation depth. Economicality and constructability were improved by implementation of specialized design and construction method. |
|
|
|
|
Detailed Design for Improvement of a Drainage Pump Station of Gasan2 |
Detailed Design for Improvement of a Drainage Pump Station of Gasan2
Period : 2007.04.30 ~ 2007.08.27
Ordering Organization : Gumcheon ward office
As improving the a Drainage Pump Station of Gasan2 that is located at 535-146, Gasan-dong, Gumcheon-Gu, disease and insect is inhibited. As providing a sports complex ,offered a site to be able to practice to the residents. We had designed to lead a better life style by making a comfortable surroundings. The plans of a facilities consist of improving water storage of 3,287m2, a improving a feed canal of 201m, setting up 3 facilities(P.E films) to reduce and prevent a bad smell, afforesting and installing a sport facility of 765m2, embanking with a stone of 145m. |
|
|
|
|
Detailed design for repairing and enhancing 4 sewer between 46-8 and 24-4 in Daejo-Dong |
Detailed design for repairing and enhancing 4 sewer between 46-8 and 24-4 in Daejo-Dong
Period : 2007.10. 8 ~ 2008.02.04
Ordering Organization : eunpyeong ward office
The purpose of this project are to secure a safety and usability of structures as carrying out economically and safely a maintenance of a decrepit and damaged sewer culvert in Eunpyeong-Gu. �� The work scope is as follows - Total Length : 1.38km - Section of Daejo-dong #46-8~224-3 : 365m(sewer culvert) - Section of eongam-dong #745-16~751-22 : 110m(sewer culvert) - Section of yeokchon-dong #66-32~74-41 : 400m(sewer culvert) |
|
|
|
|
Basic Design for Improvement of a sewer in Boryeong by BTL |
Basic Design for Improvement of a sewer in Boryeong by BTL
Period : 2007.07.02 ~ 2007.09.27
Ordering Organization : KCC Corporation
�� The scope of work is as follows. - Location : Boryeong city, Chungnam - Area : 3.47km2 - sewage pipe : 56.7km - Drainage facilities : 3,360ea The purpose of the project is to increase efficiency of a sewage treatment plant, establish a advanced system, maintain a function of a sewage pipe by monitoring on it, maintain efficiently and recovery completely a sewage pipe function by improving and constructing a existing decrepit sewer. As a result, this project will provide a improvement of a residence circumstance, a creation of a optimum benefit for a concessionaire and alleviation of a governmental liabilities. |
|
|
|
|
Detailed design for improvement of a sewer between 13 and 32 in Yeouido |
Detailed design for improvement of a sewer between 13 and 32 in Yeouido
Period : 2007.05.02 ~ 2007.07.16
Ordering Organization : Yeongdungpo ward office
The purpose of this project is to secure a comfortable life for a residents of #13~23 region in Yeouido, as improving a decrepit and bad sewer, and relocating it to be overlapped with a existing utility tunnel between #13 and 23 in Yeouido-dong. The total length of the sewer is 0.5km. Section of a lower part of a utility tunnel that is crossing with a existing pipe and a park that is difficult to construct has been planned a way of using a steel pipe. As one part of the project will be newly constructed for a exclusive pipe in order to avoid overlapping with a utility tunnel, the flow of sewage would be distributed from a existing sewer and it has been planned for the sewage water to flow smoothly. |
|
|
|
|
Detailed Design for Improvement of a open sewer facility between Gasan Digital complex and Doksan st |
Detailed Design for Improvement of a open sewer facility between Gasan Digital complex and Doksan station
Period : 2006.10. 27 ~ 2007.04.30
Ordering Organization : Gwanak ward office
After dredging a existing uncovered open-sewer that is located in a board area between Gasan Digital Complex and Doksan station, as the new sewer of 1.77km, RC manhole of 18ea, a rain-water stop-log of 79ea have been planned to be constructed, Sambo have intended a prevention of a stench, improvement of a town environment, prevention of a infectious disease , protection of a flooding damage, a preservation of water quality. Moreover, Sambo has planned in order to lead a pleasant life style as installing a protection facility of a sand outflow from a bank where is between Bodo Br. and Gumcheon Br. and establishing the maintenance plan of a puddle where is in front of a pipe for pulling out sand. |
|
|
|
|
Detailed Design for Improvement of a open sewer facility between Gasan Digital complex and Doksan st |
Detailed Design for Improvement of a open sewer facility between Gasan Digital complex and Doksan station Period : 2006.10. 27 ~ 2007.04.30
Ordering Organization : Gwanak ward office
After dredging a existing uncovered open-sewer that is located in a board area between Gasan Digital Complex and Doksan station, as the new sewer of 1.77km, RC manhole of 18ea, a rain-water stop-log of 79ea have been planned to be constructed, Sambo have intended a prevention of a stench, improvement of a town environment, prevention of a infectious disease , protection of a flooding damage, a preservation of water quality. Moreover, Sambo has planned in order to lead a pleasant life style as installing a protection facility of a sand outflow from a bank where is between Bodo Br. and Gumcheon Br. and establishing the maintenance plan of a puddle where is in front of a pipe for pulling out sand.
|
|
|
|
|
Detailed design for improvement of a sewer of Nangok interchange |
Detailed design for improvement of a sewer of Nangok interchange
Period : 2006.10.23 ~ 2006.11.21
Ordering Organization : Gwanak ward office- Sambo has implemented a improvement of a sewer as followings. - Decrepitization of a sewer facility that is placed at Nangok intercahge of #8,4,11 Sinrim-dong, Gwanak-Gu - Function of pulling over a sewage - Scope of the project is as follows - Total Length : 0.74km - Length of Sewer (Hum-type pipe : D600~D1200mm) : 0.65km - Sewage and rain-water linking pipe (Polyethylene double layer pipe : D200mm) : 0.09km - 18ea Manhole, 19ea rain-water stop-log - The purpose of this project is to lead a hygienic and pleasant city-life, and prepare for a flooding damage |
|
|
|